CASE STUDY

Advanced Drainage Systems

Build-to-suit/Own

40,000-square-foot manufacturing facility

Gastonia, North Carolina

Advanced Drainage Systems

Advanced Drainage Systems, a large manufacturer of HDPE pipe, required a new manufacturing location to serve the Carolinas market. The requirement was for a 20-acre, rail-served site. Ultimately, the site selected required complete coordination of a road extension and rail spur to meet production schedule.

  • assessed all available sites in search area,
  • coordinated contractor selection and preliminary design,
  • provided incentive analysis and negotiated final incentives, and
  • coordinated rail spur implementation and site work.

The project was completed on time and ADS was so pleased they now use this project as a model facility.

This project was developed or constructed by principals of Red Rock Developments prior to founding the company.